Romanian developer Monsson has commissioned a 24 MWh (6 MW x four hours) battery storage system as part of Romania’s first hybrid photovoltaic-wind-battery project.
Contact online >>
A perfect proof that European battery and ESS producers can successfully challenge their Asian and global competitors. A re-industrialised and energy-secure Europe is within reach!" Prime Batteries CEO Vicentiu Ciobanu
Located in Constanța county in Romania, the facility has 6 MW in operating power and a capacity of four hours, It translates to 24 MWh, making it the biggest battery energy storage system or BESS in the country.
The storage system is installed next to the Mireasa wind farm and the Galbiori solar park and will be fully connected to the grid by the end of 2024. Prime batteries are set to be charged mostly at peak production times
Romania''s Ministry of Energy has reached two additional milestones under the National Recovery and Resilience Plan related to battery storage capacities and PV panel production.
Located in Constanța county in Romania, the facility has 6 MW in operating power and a capacity of four hours, It translates to 24 MWh, making it the biggest battery energy storage system or BESS in the country.
The storage system is installed next to the Mireasa wind farm and the Galbiori solar park and will be fully connected to the grid by the end of 2024. Prime batteries are set to be charged mostly at peak production times when energy demand and prices are low.
According to the subsidiary''s data, the battery energy storage system (BESS) has 21.6 MWh in capacity, while the indicative depth of discharge was 80%. The nameplate or active capability is 5.4 MW, translating to 5 MW in effective operating power, the
The current 24 MWh storage consists of 132 battery strings with 114,048 lithium-ion cells containing 1,240 kilometres of active material electrodes. It has taken approx. 4,200 hours of engineering on the electrical part and 3,000 hours on the mechanical part – the work proudly carried out in Romania."
The current 24 MWh storage consists of 132 battery strings with 114,048 lithium-ion cells containing 1,240 kilometres of active material electrodes. It has taken approx. 4,200 hours of engineering on the electrical part and
The site is in Arad near Romania''s border with Hungary. The batteries will be the size of cargo containers, Bătrînuţ pointed out. In his words, the investment in the photovoltaic park is worth EUR 800 million while the storage unit will cost EUR 200 million.
A perfect proof that European battery and ESS producers can successfully challenge their Asian and global competitors. A re-industrialised and energy-secure Europe is within reach!" Prime Batteries CEO Vicentiu Ciobanu said the project would be increased to 216MWh in 2025.
The storage system is installed next to the Mireasa wind farm and the Galbiori solar park and will be fully connected to the grid by the end of 2024. Prime batteries are set to