In Serbia, integrating renewable energy sources into the national transmission system requires navigating through specific regulatory pathways, especially amid temporary connection halts. Elektromreža Srbije (EMS) outlines clear exemptions to these halts for projects that proactively support the grid''s stability and balance.
Serbia''s new rules for connecting solar parks and wind farms to the transmission system, operated by Elektromreža Srbije, are a test for both the state-owned company and investors, according to participants at Belgrade
After months of ironing out the details, Serbia has started applying new legislation that regulates the procedure for connection to the national power grid. Specifically, the transmission system operator, Elektromreža Srbije (EMS), has acted on renewable energy investors'' requests to sign agreements on the preparation of grid connection
Last year we secured land for 490MW of solar developments in Serbia, in line with new legislations for the country''s renewable energy development. For the most recent TSO deadline, in December 2023, we submitted four PV grid applications with accompanied BESS.
Serbia''s transmission system operator Elektromreža Srbije (EMS) has officially received 142 requests for wind and solar projects so far. Four facilities are already in operation, while connection study contracts have been signed for 33, with 105 pending.
Serbia is implementing new rules for connecting solar parks and wind farms to the transmission system. Participants at Belgrade Energy Forum discussed grid challenges, emphasizing the importance of system security, flexibility, and economic viability in
After months of ironing out the details, Serbia has started applying new legislation that regulates the procedure for connection to the national power grid. Specifically, the transmission system operator,
Dunja Grujić, Head of the Sector for the Market Support at Elektrodistribucija Srbije has revealed that 171 solar power plants with an installed capacity of 60 MW are currently connected to the distribution system of Serbia. If you add 70
Serbia''s transmission system operator, Elektromreža Srbije (EMS), has announced a delay in grid connections for new solar and wind projects lacking a grid connection study contract, citing risks to system stability from insufficient balancing reserves, writes Balkan Green Energy News.
Serbia''s transmission system operator, Elektromreža Srbije, has decided to delay the connection to the grid of solar power plants and wind farms that don''t have a contract on developing a grid connection study. However, such projects could access the network if the investors secure balancing capacity.
After months of ironing out the details, Serbia has started applying new legislation that regulates the procedure for connection to the national power grid. Specifically, the transmission system operator, Elektromreža Srbije (EMS), has acted on renewable energy investors'' requests to sign agreements on the preparation of grid connection
Serbia''s new rules for connecting solar parks and wind farms to the transmission system, operated by Elektromreža Srbije, are a test for both the state-owned company and investors, according to participants at Belgrade Energy Forum.
Serbia''s transmission system operator Elektromreža Srbije (EMS) has officially received 142 requests for wind and solar projects so far. Four facilities are already in operation, while connection study contracts have been
Dunja Grujić, Head of the Sector for the Market Support at Elektrodistribucija Srbije has revealed that 171 solar power plants with an installed capacity of 60 MW are currently connected to the distribution system of Serbia. If you add 70 MW of 3,600 prosumers, a total of 130 MW of solar is connected to the distribution system.
Serbia’s transmission system operator, Elektromreža Srbije, has decided to delay the connection to the grid of solar power plants and wind farms that don’t have a contract on developing a grid connection study. However, such projects could access the network if the investors secure balancing capacity.
The adequacy analysis assessed that Serbia’s existing production capacities could withhold solar power plants and wind farms with a combined 5,800 MW. This is close to an earlier assessment.
According to EMS’s notification, the delay doesn’t apply to projects with contracts for the development of grid connection studies. The list consists of 27 wind power projects with a total planned capacity of 4,200 MW and five future solar parks with an overall capacity of 352 MW.